On-Line Building Permit Services
Permits Home     My Account     Help


Electrical Panel Permit Requirements
The on-line permit is available for properties in Sunnyvale with a residential zoning district. Zoning district information is available on-line by clicking on E-Zoning.

This permit will allow replacement of the existing electrical panel up to a maximum of 200 amps in the same location

Following is a listing of the general requirements for electrical panel replacements based on the 2013 California Electrical Code. This brochure is intended to provide general information, contact the Building Safety Division for any questions or additional information.
  • General Requirements - The main electrical service shall be installed with rigid conduit. Electrical metallic tubing may be used where the service drop is attached to the building. The service entrance cable may be used, provided the approved fittings are used with the cable, such as a rain-tight service head or forming the cable goose-neck, taped or painted, and held securely in place by a fitting approved for the purpose. (Article 230)

    The minimum size service conduit shall be 1-1/4”. The minimum size service entrance wire shall be rated 100 amperes minimum for single family dwellings. For single family homes, the service disconnect means shall have a rating of less than 100 amperes, 3-wire. A larger service may be required for new homes or additions to existing homes based on the actual load calculations. (CEC 230.79(c))

  • Service Entrance Conductors (Wires) – Conductors that extend across a roof shall have a minimum vertical clearance of 3’ above the roof surface for roofs sloped 4:12 or more (18” clearance required when conductors enter through the roof overhang/eave). The service head shall be located so that the service drops, together with the open wires between the service head and service drop, will have a minimum clearance of 10’ vertically above ground and 3’ radius from doors and windows. (Article 230.24)

    The neutral (grounded) conductor must be identified with white tape at both terminals. (Article 200.6)

    Service entrance conductors and cables shall be approved for a wet location and, when exposed to direct sunlight, shall be listed and marked as “sunlight resistant.” Service entrance conductors and conduit shall be sized according to the following table (CEC Table 310.5(b)(7) and chapter 9 table 1):
           
    SERVICE ENTRANCE CONDUCTORS SIZE AND RATING
    Service or Feeder
    Rating
    Copper Conductors Aluminum or Copper-Clad
    Aluminum
    Minimum Conduit
    Size
    100 Amps #4 AWG #2 AWG 1 ¼ inch
    125 Amps #2 AWG #1/0 AWG 1 ¼ inch
    150 Amps #1 AWG #2/0 AWG 1 ¼ inch
    200 Amps #2/0 AWG #4/0 AWG 1 ½ inch
    The grounding conductors must be identified by white or grey tape at both ends (200.6).

  • Meter location - The height of the meter shall be between 48” and 66” above the ground. Note: PG&E prohibits new meters on exterior walls adjacent to bedrooms or bedroom closets. A minimum horizontal clearance of 36” from the gas meter and piping is required.

  • Working space - The clear working space in front of the panel shall be 30” wide by 36” deep with a minimum headroom clearance of 6’-6” (Article 110.26)

  • Grounding of Services - Grounding shall consist of a continuous grounding electrode conductor run from the panel to a ground rod (grounding electrode) and to the cold water pipe. Grounding of the electrical service at the main water line must be within the first 5’ of water piping into the building. The underground water service shall not be used as the grounding electrode without supplemental electrode. [CEC 250.52 (A)(1) and 250.53 (I)]

    For new structures and additions to existing structures, a concrete encased ground electrode shall be installed. This shall consist of 20’ of ½” bare or zinc-coated rebar or bare copper wire in the portion of the footing in contact with earth. (CEC 250.50)

    For existing structures, the grounding electrode shall be nonferrous (copper), listed, and not be less than ½” in diameter. The electrode shall be installed such that at least 8’ of length is in contract with the soil. The upper end of the electrode shall be flush with or below ground level unless the above-ground end and the grounding electrode conductor attachment is protected against physical damage. [CEC 250.52 (A)(5) and 250.53 (D)]

    The required grounding electrode conductor (from electrode to panel) size is listed in the following table:
           
    GROUNDING ELECTRODE CONDUCTOR SIZING (Table 250.66)
    Size of Main Panel Copper Conductors Aluminum or Copper-Clad Aluminum
    100 Amps #8 AWG #6 AWG
    125 Amps #8 AWG #6 AWG
    150 Amps #6 AWG #4 AWG
    200 Amps #4 AWG #2 AWG


  • Bonding - Bonding of the hot, cold, and gas lines is required when the electrical panel is replaced. Bonding of the hot, cold, and gas lines is required with water service replacements (if using a less conductive material than is existing) and for all re-pipes. Bonding shall consist of a continuous bond jumper installed at the water heater between the hot, cold, and gas lines. The bonding jumper shall be sized based on the following table:
           
    BONDING JUMPER SIZING (Table 250.122)
    Size of Main Panel Copper Conductors Aluminum or Copper-Clad Aluminum
    100 Amps #8 AWG #6 AWG
    125 Amps #6 AWG #4 AWG
    150 Amps #6 AWG #4 AWG
    200 Amps #6 AWG #4 AWG

The Electrical Panel Permit is NOT available on-line if you are:
  • Installing the new electrical panel in a different location.
  • Installing a new electrical panel larger than 200 amps.
  • Installing additional sub-panels with the new electrical panel.
  • Performing additional electrical work in conjunction with the new electrical panel installation.
If any of the above conditions apply, the permit shall be issued at the One-Stop Permit Center, City Hall, 456 W Olive Avenue. Specific process information is available at the Building Division web site.

Inspections
  • A minimum of two inspections are required, a utility release and a final. The utility release inspection should be scheduled when the new panel is installed and ready to be hooked up the PG&E supply. The building inspector will provide a utility release form which will need to be provided to PG&E to have the supply hooked up to the new panel. A wire lath inspection is required for stucco repairs. A final inspection should be scheduled after all of the work is complete.
City of Sunnyvale Community Development E-OneStop